Climbing frame group hanging electric hoist commissioning procedures


Climbing frame group hanging electric hoist is attached to the wall by climbing frame lifting power wan buckle frame rack or ordinary steel fasteners and building climbing frame control cabinet composed of three parts, the popular saying is that you can be a dozen layers or whether dozens of buildings layer, as long as the erection of a wall scaffolding,Manual hoist coupled with climbing frame group hanging electric hoist as a hoist, electric control box for the operating center system, will be able to fully meet the cabinet structure, the following for you to explain the commissioning process.
1, group hanging electric hoist Before commissioning,load chain the construction unit shall organize, on behalf of the owners, supervision unit representatives, supplier representatives and owners of motor Ministry will participate in all pre-installation inspection and acceptance, in line with the design and specification requirements, commissioning work can be carried out.
2, the preparatory work before commissioning
A, electrical systems, safety interlocks, actuators, controllers, lighting and signal systems shall comply with safety requirements, the action should be sensitive and accurate.
B, fixed rope end and a hook and wound on the reel should be correct,hoist and trolley reliable, secure ropes compliance.
C, lubricate all lubrication points should be explained by oil were added.
D, all parts of the shell-proof bolts one by one check, you must tighten the sealing reliable.
E, when the line is energized, check the direction of the manipulation-proof control button should be explosion-proof electric hoist crane group movement in the same direction.
F, using the formal lifting limit switch limit switch position should be preceded by checking whether the lifting motor running in the same direction, or should change the wiring.